
Case Study
Data Centre Clean Agent / Gas Suppression System Design Concentration and Cylinder Capacity Assessment
Nov 2026
Direct Engineering Answer
The illustrative protected-room gross volume is 2,000 m² × 4 m = 8,000 m³. The example assumes a 640 kg agent calculation output and 80 kg per cylinder, resulting in 8 cylinders. These assumptions do not establish a real agent concentration or final cylinder bank; the selected manufacturer’s approved calculation and enclosure assessment govern.
1. Project Background
This case study demonstrates an illustrative engineering approach for assessing a clean-agent total-flooding fire suppression system for a data-centre protected room. The calculation establishes the protected volume, explains the relationship between design concentration and agent quantity, demonstrates an illustrative cylinder-capacity calculation, and identifies the associated enclosure-integrity, discharge and pressure-relief requirements. Final agent quantity and cylinder configuration shall be generated using the selected agent manufacturer’s approved/listed design software and the applicable project requirements.
2. Facility / System Profile
| Parameter | Illustrative Design Basis | Engineering Relevance |
| Facility | Data centre | Mission-critical environment. |
| Protected room | IT Hall / UPS room | Total-flooding suppression application. |
| Room floor area | 2,000 m² | Volume input. |
| Clear room height | 4 m | Volume input. |
| Gross room volume | 8,000 m³ | Preliminary protected volume. |
| Illustrative design concentration | 10% | Methodology example only. |
| Design temperature | 20°C | Affects agent calculation. |
| Illustrative agent mass | 640 kg | Assumed calculation output. |
| Illustrative cylinder fill | 80 kg/cylinder | Demonstration of cylinder count. |
3. Engineering Challenge
Clean-agent design is not a simple volume-to-cylinder conversion. The final agent quantity depends on the selected agent, hazard, minimum design concentration, design temperature, net protected volume, altitude where relevant, cylinder filling limits and the manufacturer’s approved calculation method. The room must also retain the agent concentration for the required hold period and safely accommodate the pressure transient generated during discharge.
- Verify the protected room geometry.
- Determine the net protected volume.
- Confirm the selected agent and applicable design concentration.
- Determine total agent mass using the approved calculation method.
- Select cylinder size and fill quantity.
- Calculate cylinder quantity.
- Complete nozzle and pipe hydraulic design.
- Assess enclosure integrity and pressure relief.
- Coordinate detection, release and HVAC shutdown.
4. Engineering Basis and Reference Framework
The governing design basis should comprise the approved data-centre fire strategy, selected clean agent, manufacturer’s listed design methodology, applicable clean-agent standards, actual room geometry, enclosure construction and project requirements. The numerical values below are illustrative and are not universal clean-agent design parameters.
| Reference / Input | Application |
| Approved Fire Strategy | Defines protected hazard and suppression objective. |
| Selected Agent Manufacturer | Provides certified design calculation method. |
| Clean-Agent Standard | Defines system design/installation framework where applicable. |
| Room Architectural Data | Defines protected volume and enclosure. |
| Nozzle/Pipe Design | Defines discharge distribution. |
| Enclosure Integrity Test | Verifies retention of design concentration. |
5. Existing Conditions / Assessment Basis
- The illustrative room area is 2,000 m².
- Clear room height is 4 m.
- Gross room volume is therefore 8,000 m³.
- A 10% concentration is used solely for demonstrating the calculation workflow.
- An assumed 640 kg agent requirement is used to demonstrate cylinder selection.
- Each illustrative cylinder is assumed to contain 80 kg.
- Actual agent type, concentration and quantity are not established by this case study.
6. Engineering Methodology
- Verify actual room dimensions.
- Determine net protected volume using the approved calculation method.
- Select the specific clean agent.
- Confirm minimum design concentration for the identified hazard.
- Confirm design temperature and any altitude correction.
- Generate total agent mass using manufacturer-approved software.
- Select approved cylinder fill quantity.
- Round cylinder quantity upward to a complete approved configuration.
- Complete nozzle, pipe and discharge-time calculations.
- Complete enclosure-integrity and pressure-relief assessment.
7. Illustrative Protected Volume Calculation
Room floor area = 2,000 m²
Clear room height = 4 m
Gross room volume = 2,000 × 4 = 8,000 m³
The 8,000 m³ result is a gross geometric volume. Final agent calculations shall use the selected manufacturer’s approved method to establish the net protected volume, including applicable deductions or exclusions.
8. Design Concentration Assessment
For demonstration, assume an illustrative design concentration of 10%. This value is intentionally generic and must not be adopted for a real system without confirming the selected agent, hazard classification, minimum design concentration and applicable standard.
Illustrative design concentration = 10%
The concentration establishes the target extinguishing/suppression atmosphere. It does not by itself establish the agent mass because the physical properties of the selected agent and design temperature are required.
9. Agent-Mass Calculation Workflow
- Confirm selected agent.
- Confirm minimum design concentration.
- Confirm design temperature.
- Confirm net protected volume.
- Enter approved inputs into the manufacturer’s design software.
- Obtain calculated total agent mass.
- Verify cylinder fill limitations and approved manifold arrangement.
For this case study, the approved calculation output is assumed to be 640 kg solely to demonstrate the subsequent cylinder-capacity calculation.
10. Illustrative Cylinder Capacity Calculation
Assumed total calculated agent requirement = 640 kg
Assumed approved cylinder fill = 80 kg/cylinder
Cylinder quantity = 640 ÷ 80 = 8 cylinders
Illustrative cylinder bank = 8 cylinders
If the calculated agent mass does not divide exactly by the approved cylinder fill, the quantity shall be rounded up to the next complete approved cylinder configuration. The actual cylinder fill must comply with the selected manufacturer’s approved filling limits.
11. Illustrative Cylinder Schedule
| Item | Illustrative Value | Engineering Check |
| Total agent requirement | 640 kg | Manufacturer calculation output – assumed. |
| Cylinder size/fill | 80 kg | Manufacturer-approved configuration required. |
| Calculated quantity | 8 cylinders | 640 ÷ 80. |
| Bank arrangement | 8-cylinder bank | Final manifold design required. |
| Reserve philosophy | Project-specific | Confirm whether reserve cylinders are required. |
12. Enclosure Integrity Assessment
A clean-agent total-flooding system depends on the protected enclosure retaining the required concentration. Open doors, unsealed cable penetrations, HVAC openings or construction defects can compromise system performance.
- Verify room boundaries.
- Seal cable and pipe penetrations.
- Verify door seals.
- Coordinate HVAC shutdown and damper closure.
- Provide approved pressure-relief arrangements.
- Conduct enclosure integrity testing where required.
- Rectify leakage before final acceptance.
13. Pressure-Relief Consideration
Gas discharge can create a pressure transient inside the protected room. Pressure relief must therefore be assessed from the selected agent, discharge rate, room construction, leakage characteristics and manufacturer’s approved calculation.
Pressure-relief sizing cannot be established from agent mass alone. The final relief arrangement must be coordinated with the clean-agent system manufacturer and the room/enclosure design.
14. Discharge and Piping Engineering
| Design Item | Engineering Requirement |
| Cylinder manifold | Sized for simultaneous discharge arrangement. |
| Distribution piping | Hydraulically designed for approved discharge time. |
| Nozzles | Selected and located to achieve required concentration distribution. |
| Discharge time | As required by approved agent/system design. |
| Pressure relief | Designed for discharge pressure transient. |
| HVAC | Shutdown/damper logic coordinated. |
| Detection | Automatic release sequence coordinated. |
15. Cause-and-Effect Sequence
- Fire/smoke detection initiates alarm.
- Pre-discharge alarm operates where specified.
- Time delay operates where approved.
- HVAC shutdown/dampers operate.
- Manual abort function operates where provided.
- Clean-agent release command operates.
- Cylinder bank discharges.
- Pressure relief operates as designed.
- Fire alarm and supervisory status are transmitted.
- System remains in post-discharge/lockout state until authorised restoration.
16. Engineering Solution
- Use the selected agent manufacturer’s approved calculation software for final agent quantity.
- Verify actual net protected volume.
- Confirm the minimum design concentration for the specific hazard.
- Select cylinders based on approved fill limits.
- Hydraulically design the distribution piping and nozzles.
- Verify enclosure integrity and pressure relief.
- Coordinate fire alarm, HVAC, BMS/DCIM and release interfaces.
- Document the final cylinder bank, nozzle layout and cause-and-effect.
17. Engineering Coordination Matrix
| Engineering Discipline | Key Interface | Verification |
| Fire Alarm | Detection and release | Cause-and-effect test. |
| Clean Agent | Agent quantity and cylinder bank | Manufacturer calculation. |
| Mechanical/HVAC | Shutdown and dampers | Functional test. |
| Architecture | Room enclosure | Integrity inspection. |
| Electrical | Power/control supply | Functional verification. |
| BMS/DCIM | Alarm/status monitoring | Interface test. |
| Operations | Abort/release/restoration | Procedure and training. |
18. Coordination and Execution Challenges
- Room volume can change when architectural partitions are modified.
- Unsealed cable penetrations can compromise total-flooding performance.
- Incorrect cylinder fill selection can invalidate the approved design.
- Pressure-relief requirements must be coordinated with room construction.
- HVAC shutdown logic must be tested under actual operating conditions.
- IT operations may restrict discharge testing, requiring controlled commissioning arrangements.
- Battery/electrical hazards may require a different suppression strategy than an IT room.
19. Testing, Commissioning and Acceptance
- Verify room dimensions and final protected volume.
- Verify agent type and cylinder fill.
- Verify cylinder quantity and manifold configuration.
- Verify nozzle quantity and location.
- Verify piping installation.
- Conduct enclosure integrity test where required.
- Verify HVAC shutdown/damper operation.
- Verify pressure-relief installation.
- Test cause-and-effect sequence.
- Record final cylinder pressure/weight data as applicable.
- Complete commissioning and handover documentation.
20. Engineering Outcome
| Outcome | Illustrative Result |
| Protected room area | 2,000 m². |
| Clear room height | 4 m. |
| Gross protected volume | 8,000 m³. |
| Illustrative concentration | 10%. |
| Illustrative agent requirement | 640 kg – assumed calculation output. |
| Illustrative cylinder fill | 80 kg/cylinder. |
| Illustrative cylinder quantity | 8 cylinders. |
| Primary engineering controls | Agent calculation, enclosure integrity, hydraulics and pressure relief. |
| Final acceptance | Requires selected-agent manufacturer calculation and approved project design. |
21. Lessons Learned
- Clean-agent quantity cannot be finalised from room volume alone.
- Design concentration must be tied to the selected agent and hazard.
- Cylinder quantity follows the approved calculated agent mass and filling configuration.
- Enclosure integrity is essential for total-flooding performance.
- Pressure relief is a critical room-design interface.
- Discharge piping and nozzle hydraulics require manufacturer-approved calculation.
- Final cause-and-effect testing is essential before handover.
22. Design Review Checklist
☐ Agent selected and approved
☐ Hazard classification confirmed
☐ Actual room volume verified
☐ Net protected volume established
☐ Design concentration confirmed
☐ Design temperature confirmed
☐ Manufacturer calculation completed
☐ Total agent mass verified
☐ Cylinder fill verified
☐ Cylinder quantity verified
☐ Nozzle/piping calculation completed
☐ Enclosure integrity verified
☐ Pressure relief verified
☐ Cause-and-effect tested
☐ Final O&M documentation issued
23. Related Engineering Content
| Content Type | Reference |
| Engineering Calculation | EC-100 – Data Centre Clean Agent / Gas Suppression System Design Concentration and Cylinder Capacity Assessment |
| Previous Calculation | EC-099 – Data Centre Fire Protection System Capacity and Critical Infrastructure Risk Assessment |
| Related Case Study | CS-099 – Data Centre Fire Protection System Capacity and Critical Infrastructure Risk Assessment |
| Related White Paper | Data Centre Clean-Agent Fire Suppression, Design Concentration, Cylinder Capacity and Enclosure Integrity |
| Related FAQs | Clean Agent; Gas Suppression; Design Concentration; Agent Quantity; Cylinder Capacity; Enclosure Integrity; Pressure Relief; Discharge Time |
| Related Engineering Diagram | ED-100 – Data Centre Clean-Agent Cylinder Bank, Manifold, Distribution Piping, Nozzles, Pressure Relief and Protected Room |
24. Source Basis and Engineering Qualification
The 2,000 m² room, 4 m height, 8,000 m³ gross volume, 10% illustrative concentration, 640 kg assumed agent mass and 80 kg cylinder fill used in this case study are engineering assumptions created to demonstrate the methodology. They are not project-recorded data, universal clean-agent parameters or contractual acceptance criteria. Final design shall use the selected agent manufacturer’s approved/listed calculation, actual enclosure data, applicable standards and project requirements.
