
Case Study
IBMS Graphics, HMI and Operator Workstation Assessment
Nov 2026
Direct Engineering Answer
The illustrative HMI assessment maps 95 unique points across four navigation levels and 40 graphics pages. Five pages require correction, giving a 12.5% correction ratio. Final graphics must be validated against the approved point list, alarm philosophy, authorised command functions and installed equipment during SAT.
1. Project Background
This case study presents an illustrative engineering approach for developing and validating IBMS graphics and the operator workstation Human-Machine Interface (HMI). The objective is to convert approved point lists, alarm philosophy and system architecture into a clear operator interface that supports monitoring, alarm recognition, equipment status and approved control functions. Final graphics shall follow the approved project HMI philosophy, equipment data, cause-and-effect and functional requirements.
2. Facility / System Profile
| Parameter | Design Basis | Engineering Relevance |
| Facility | Commercial / critical facility | Requires central operational visibility. |
| IBMS Server | Central supervisory application | Hosts graphics and alarm management. |
| Operator Workstations | 2 illustrative stations | Provide user interface for operations. |
| Graphics Levels | Campus → Building → Floor → Equipment | Supports hierarchical navigation. |
| Integrated Systems | HVAC, electrical, fire/status and ELV | Requires consistent visualisation. |
| Alarm Interface | Prioritised alarms/events | Supports operator response. |
3. Engineering Challenge
Poorly structured graphics can make a technically functional IBMS difficult to operate. The engineering challenge is to create a hierarchy in which operators can navigate from system overview to equipment detail, identify abnormal conditions quickly and access only the controls authorised by the approved operating philosophy.
- Establish a consistent graphics hierarchy.
- Map approved points to graphical objects.
- Provide clear status and alarm indication.
- Differentiate monitoring from command functions.
- Validate navigation and equipment naming.
- Ensure graphics reflect actual field equipment.
- Standardise screen layouts, symbols and engineering units.
4. Engineering Basis and Applicable References
The engineering framework for this library identifies the approved IBMS architecture, master point list, alarm philosophy, cause-and-effect matrix, OEM equipment information and project HMI specification as the governing basis. Exact graphics, colours, navigation and control permissions are project-specific and shall be approved before implementation.
| Reference | Engineering Application |
| Approved IBMS Architecture | Defines system hierarchy and workstation functions. |
| Master Point List | Defines source points represented on graphics. |
| Alarm Philosophy | Defines priority and abnormal-condition presentation. |
| Cause-and-Effect Matrix | Defines approved actions and interlocks. |
| OEM Equipment Data | Supports accurate equipment graphics/statuses. |
| Project HMI Specification | Defines screen format, navigation and user requirements. |
5. Existing Conditions / Assessment Basis
- The illustrative IBMS contains 95 unique points from the previous point-list assessment.
- These points are distributed across HVAC, electrical, fire/status and ELV interfaces.
- The proposed HMI uses four navigation levels.
- An illustrative 40 equipment graphics pages are required.
- Five pages initially contain incomplete or inconsistent point mapping.
- All quantities and configurations are illustrative.
6. Engineering Methodology
- Establish the approved HMI navigation hierarchy.
- Create a master equipment-to-graphic mapping schedule.
- Map approved points to graphical objects.
- Configure alarm/status presentation.
- Define equipment detail pages.
- Restrict command objects to approved functions.
- Review graphics against actual equipment and drawings.
- Conduct operator usability and functional testing.
- Freeze the approved graphics package for SAT and handover.
7. Illustrative HMI Hierarchy
| Level | Illustrative Screen | Purpose |
| Level 1 | Facility Overview | High-level operational status. |
| Level 2 | Building / System Overview | System-level navigation. |
| Level 3 | Floor / Plant Overview | Equipment grouping and status. |
| Level 4 | Equipment Detail | Detailed values, alarms and approved controls. |
8. Illustrative Graphics Mapping Assessment
| Graphic Category | Pages | Points Represented | Initial Issues |
| HVAC | 20 | 45 | 3 pages with mapping discrepancies. |
| Electrical / Power | 8 | 25 | 1 page with inconsistent naming. |
| Fire / Life-Safety Status | 4 | 15 | 1 page requiring alarm text correction. |
| ELV / Security | 8 | 10 | No major issue. |
| Total | 40 | 95 | 5 pages requiring correction. |
9. Illustrative Graphics Correction Ratio
Initial graphics pages = 40
Pages requiring correction = 5
Correction ratio = 5 ÷ 40 × 100 = 12.5%
Illustrative graphics correction ratio = 12.5%
This ratio is a project-control indicator only and is not a universal HMI quality benchmark.
10. Engineering Solution
- Use a consistent navigation hierarchy from facility overview to equipment detail.
- Maintain identical equipment tags across drawings, point lists and graphics.
- Display engineering units and equipment status clearly.
- Use approved alarm priorities from the master alarm matrix.
- Restrict commands to approved operator functions.
- Provide clear indication of communication loss or stale data.
- Validate graphics against field equipment during SAT.
- Maintain a controlled graphics revision register.
11. HMI Functional Matrix
| Function | Engineering Check | Verification |
| Navigation | All approved screens accessible | Operator test. |
| Point Display | Correct value/status shown | Field comparison. |
| Alarm | Correct priority and text | Alarm simulation. |
| Equipment Status | Run/stop/fault correctly displayed | Functional test. |
| Command | Only authorised commands available | Command test. |
| Communication | Loss/failure identified | Network/interface test. |
| History/Trend | Required points trend correctly | Historian test. |
12. Coordination and Execution Challenges
- Graphic tags can diverge from equipment naming if revisions are not controlled.
- Point-list changes can leave obsolete graphics objects.
- Alarm colours and priorities must remain consistent with the approved philosophy.
- Commands shown on graphics may create operational risk if not authorised.
- Communication failures should be visually distinguishable from actual equipment faults.
- Late architectural or equipment changes can require graphic revisions.
13. Testing, Commissioning and Acceptance
- Verify every approved graphic against the master screen register.
- Check navigation between all hierarchy levels.
- Verify point values and engineering units.
- Simulate representative equipment alarms.
- Verify alarm priority and text.
- Test approved command functions.
- Verify communication-loss indication.
- Check trends, event logs and historical values where specified.
- Record SAT results and close discrepancies.
- Issue final approved graphics and screen register.
14. Engineering Outcome
| Outcome | Engineering Result |
| Facility | Illustrative commercial / critical facility. |
| Unique Points | 95. |
| HMI Levels | 4. |
| Graphics Pages | 40. |
| Pages Requiring Initial Correction | 5. |
| Illustrative Correction Ratio | 12.5%. |
| Primary Deliverable | Controlled IBMS HMI graphics and screen register. |
| Final Acceptance | Requires point mapping, alarm validation, command verification and SAT closure. |
15. Lessons Learned
- IBMS graphics are an operational engineering deliverable, not merely a visual interface.
- Consistent equipment naming is essential for troubleshooting.
- Every displayed value should trace back to an approved point.
- Alarm presentation must follow the approved alarm philosophy.
- Command availability should be explicitly authorised.
- Final graphics must be validated against the installed system before handover.
16. Design Review Checklist
☐ HMI hierarchy approved
☐ Screen register prepared
☐ Equipment naming standardised
☐ Point mapping verified
☐ Engineering units checked
☐ Alarm priorities verified
☐ Alarm text checked
☐ Command permissions reviewed
☐ Communication-loss indication checked
☐ Trends/history verified
☐ SAT completed
☐ Final graphics package issued
17. Related Engineering Content
| Content Type | Reference |
| Engineering Calculations | EC-066 to EC-075 – ELV & IBMS; EC-069 – IBMS Graphics, HMI and Operator Workstation Assessment |
| Related Case Studies | CS-066 – Point List; CS-067 – BACnet/Modbus Integration; CS-068 – Alarm Priority/Cause-and-Effect |
| Related White Paper | IBMS HMI Graphics, Operator Workstation and Visualisation Engineering |
| Related FAQs | IBMS Graphics; HMI; Operator Workstation; Screen Hierarchy; Alarm Display; Trends; Command Functions |
| Related Engineering Diagram | ED-069 – IBMS HMI Hierarchy and Operator Navigation Architecture |
18. Source Basis and Engineering Qualification
The 95 points, 40 graphics pages, four HMI levels and five pages requiring correction in this case study are illustrative engineering assumptions created to demonstrate HMI governance. They are not claimed as project-recorded data, universal HMI benchmarks or contractual requirements. Final graphics shall be based on approved project data, equipment schedules, point lists and HMI specifications.
