Diesel Generator (DG) Capacity Calculation

Engineering Calculation

Diesel Generator (DG) Capacity Calculation

Nov 2026

At a Glance

Resource ID EC-088
Essential Load P | 120 | kW
Power Factor PF | 0.80 | –
Engineering Reserve M | 20 | %
Calculated DG Load S | 150 | kVA
Required Capacity with Reserve Sreq | 180 | kVA
Source detail Refer to Technical Content
Source detail Refer to Technical Content

Calculation Method & Worked Example

Area: A = L × W

Detector Quantity: N = A / C

Area = 30 × 18 = 540 m²

Detector Quantity = 540 ÷ 81 = 6.67

Round Up = 7 Smoke Detectors.

Room Area: 540 m²
Coverage: 81 m² per detector
Calculated Quantity: 6.67
Required Quantity: 7 Nos.

Applicable Standards Listed in the Source

ISO 8528 Reciprocating Internal Combustion Engine Driven Alternating Current Generating Sets
IEC 60034 Rotating Electrical Machines
IEC 60364 Low Voltage Electrical Installations
NFPA 110 Emergency and Standby Power Systems where applicable
Manufacturer Manual Generator rating, transient response, fuel and installation requirements

Technical Content

1. Purpose

To determine the minimum diesel generator capacity required to supply the essential electrical load during utility power failure while allowing an appropriate engineering reserve.

2. Engineering Objective

To establish the DG apparent-power rating from the essential load, power factor and engineering reserve, while considering motor starting and transient loading.

3. Applicable Standards

Standards and descriptions are reproduced from the source document.

4. Design Inputs

Essential Load | P | 120 | kW
Power Factor | PF | 0.80 | –
Engineering Reserve | M | 20 | %
Calculated DG Load | S | 150 | kVA
Required Capacity with Reserve | Sreq | 180 | kVA

5. Assumptions

The essential connected load is 120 kW. An operating power factor of 0.80 and a 20% engineering reserve are adopted for the worked example. Motor starting and transient requirements shall be checked separately during final DG selection.

6. Formula(s)

Area: A = L × W
Detector Quantity: N = A / C
Final Quantity = Round Up(N)

Area: A = L × W
Detector Quantity: N = A / C
Final Quantity = Round Up(N)

Room Area: 540 m²
Coverage: 81 m² per detector
Calculated Quantity: 6.67
Required Quantity: 7 Nos.

7. Variables Explained

S = Apparent power (kVA), P = Essential load (kW), PF = Power factor, M = Engineering margin, Sreq = Required DG capacity (kVA).

8. Step-by-Step Calculation

Area = 30 × 18 = 540 m²
Detector Quantity = 540 ÷ 81 = 6.67
Round Up = 7 Smoke Detectors.

Area = 30 × 18 = 540 m²
Detector Quantity = 540 ÷ 81 = 6.67
Round Up = 7 Smoke Detectors.

Room Area: 540 m²
Coverage: 81 m² per detector
Calculated Quantity: 6.67
Required Quantity: 7 Nos.

9. Worked Engineering Example

A facility with an essential load of 120 kW at 0.80 power factor requires 150 kVA of DG capacity before reserve. With a 20% engineering reserve, the calculated requirement is 180 kVA; the next suitable standard rating is 200 kVA, subject to motor-starting verification.

10. Engineering Output

Room Area: 540 m²
Coverage: 81 m² per detector
Calculated Quantity: 6.67
Required Quantity: 7 Nos.

Room Area: 540 m²
Coverage: 81 m² per detector
Calculated Quantity: 6.67
Required Quantity: 7 Nos.

Room Area: 540 m²
Coverage: 81 m² per detector
Calculated Quantity: 6.67
Required Quantity: 7 Nos.

Room Area: 540 m²
Coverage: 81 m² per detector
Calculated Quantity: 6.67
Required Quantity: 7 Nos.

11. Design Considerations

Verify essential loads, motor starting current, step loading, alternator performance, ambient conditions, altitude, fuel system, exhaust and applicable project requirements before final DG selection.

12. Common Design Mistakes

Sizing the DG only from connected kW, ignoring motor starting, using an unsupported power factor, omitting future load growth, or selecting a rating without checking transient performance.

13. Practical Site Notes

Coordinate DG sizing with ATS/AMF panels, essential LT panels, UPS systems, motor loads, fuel storage, ventilation, exhaust and acoustic requirements.

14. Limitations

Preliminary DG sizing calculation only. Final selection shall be validated against the approved essential load schedule, OEM performance data, starting requirements and project specifications.

15. Related Engineering Systems

Essential LT Panels, ATS/AMF Panels, UPS Systems, Motors, HVAC, Fire Pumps, Fuel System, Battery Charger and Earthing System.

16. Keywords (15)

Diesel Generator, DG Capacity, Generator Sizing, Emergency Power, Essential Load, Power Factor, kVA Calculation, AMF Panel, ATS, Electrical Engineering, Standby Power, Generator Selection, Engineering Calculation, Motor Starting, Electrical System

17. AI Search Summary

DG capacity is determined by converting the essential load from kW to kVA using power factor and applying an engineering reserve. For 120 kW at 0.80 power factor, the base requirement is 150 kVA; with 20% reserve, a 200 kVA DG is the next suitable standard rating, subject to starting-load verification.

Frequently Asked Questions

What is the purpose of EC-088?

To determine the minimum diesel generator capacity required to supply the essential electrical load during utility power failure while allowing an appropriate engineering reserve.

What result does the source example report?

A facility with an essential load of 120 kW at 0.80 power factor requires 150 kVA of DG capacity before reserve. With a 20% engineering reserve, the calculated requirement is 180 kVA; the next suitable standard rating is 200 kVA, subject to motor-starting verification.

Can this preliminary calculation be used as final design approval?

Preliminary DG sizing calculation only. Final selection shall be validated against the approved essential load schedule, OEM performance data, starting requirements and project specifications.

What should be checked before final selection or implementation?

Verify essential loads, motor starting current, step loading, alternator performance, ambient conditions, altitude, fuel system, exhaust and applicable project requirements before final DG selection.