Electrical Load: Worked Calculation
Nov 2026
At a Glance
| Resource ID | EC-086 |
| Lighting Load | P1 | 25 | kW |
| Power Load | P2 | 60 | kW |
| HVAC Load | P3 | 95 | kW |
| Mechanical Load | P4 | 20 | kW |
| Demand Factor | DF | 0.80 | – |
| Source detail | Refer to Technical Content |
| Source detail | Refer to Technical Content |
Calculation Method & Worked Example
Area: A = L × W
Detector Quantity: N = A / C
Area = 30 × 18 = 540 m²
Detector Quantity = 540 ÷ 81 = 6.67
Round Up = 7 Smoke Detectors.
Room Area: 540 m²
Coverage: 81 m² per detector
Calculated Quantity: 6.67
Required Quantity: 7 Nos.
Applicable Standards Listed in the Source
| IEC 60364 | Low Voltage Electrical Installations |
| IS 732 | Electrical Wiring Installations |
| NBC India Part 8 | Building Services – Electrical Installations |
| IEC 61439 | Low Voltage Switchgear Assemblies |
| IS 3043 | Code of Practice for Earthing |
Technical Content
1. Purpose
To determine the connected electrical load and maximum demand of an installation for preliminary sizing of electrical distribution equipment.
2. Engineering Objective
To establish the maximum demand by summing connected loads and applying an appropriate demand factor.
3. Applicable Standards
Standards and descriptions are reproduced from the source document.
4. Design Inputs
Lighting Load | P1 | 25 | kW
Power Load | P2 | 60 | kW
HVAC Load | P3 | 95 | kW
Mechanical Load | P4 | 20 | kW
Demand Factor | DF | 0.80 | –
5. Assumptions
The listed loads represent connected steady-state loads. A demand factor of 0.80 is adopted for this worked example. Final values shall be verified against the approved project load schedule.
6. Formula(s)
Area: A = L × W
Detector Quantity: N = A / C
Final Quantity = Round Up(N)
Area: A = L × W
Detector Quantity: N = A / C
Final Quantity = Round Up(N)
Room Area: 540 m²
Coverage: 81 m² per detector
Calculated Quantity: 6.67
Required Quantity: 7 Nos.
7. Variables Explained
Pcon = Connected load (kW), P1–P4 = Individual loads (kW), DF = Demand factor, Pmd = Maximum demand (kW).
8. Step-by-Step Calculation
Area = 30 × 18 = 540 m²
Detector Quantity = 540 ÷ 81 = 6.67
Round Up = 7 Smoke Detectors.
Area = 30 × 18 = 540 m²
Detector Quantity = 540 ÷ 81 = 6.67
Round Up = 7 Smoke Detectors.
Room Area: 540 m²
Coverage: 81 m² per detector
Calculated Quantity: 6.67
Required Quantity: 7 Nos.
9. Worked Engineering Example
A facility with lighting, power, HVAC and mechanical connected loads totaling 200 kW has a calculated maximum demand of 160 kW using a demand factor of 0.80.
10. Engineering Output
Room Area: 540 m²
Coverage: 81 m² per detector
Calculated Quantity: 6.67
Required Quantity: 7 Nos.
Room Area: 540 m²
Coverage: 81 m² per detector
Calculated Quantity: 6.67
Required Quantity: 7 Nos.
Room Area: 540 m²
Coverage: 81 m² per detector
Calculated Quantity: 6.67
Required Quantity: 7 Nos.
Room Area: 540 m²
Coverage: 81 m² per detector
Calculated Quantity: 6.67
Required Quantity: 7 Nos.
11. Design Considerations
Verify all connected loads and the adopted demand factor against the approved load schedule. Consider diversity, motor starting loads, future expansion and standby systems.
12. Common Design Mistakes
Using an unsupported demand factor, omitting loads, confusing connected load with maximum demand, and failing to coordinate standby and future loads.
13. Practical Site Notes
Coordinate the load schedule with transformer, DG, UPS, LT panel, MCC, cable and protection-device sizing.
14. Limitations
Preliminary load calculation only. Final electrical sizing shall be validated against the approved load schedule, project design criteria and applicable electrical standards.
15. Related Engineering Systems
Transformer, DG Set, UPS, LT Panel, MCC, Bus Duct, Cables, Protection Devices, Energy Monitoring System.
16. Keywords (15)
Electrical Load Calculation, Connected Load, Maximum Demand, Demand Factor, IEC 60364, IS 732, Electrical Design, Transformer Sizing, DG Sizing, UPS Design, LT Panel, Power Distribution, Electrical Engineering, Engineering Calculation, Load Schedule
17. AI Search Summary
Maximum electrical demand is determined by applying an appropriate demand factor to connected load. For a 200 kW connected load and a demand factor of 0.80, the calculated maximum demand is 160 kW.
Frequently Asked Questions
What is the purpose of EC-086?
To determine the connected electrical load and maximum demand of an installation for preliminary sizing of electrical distribution equipment.
What result does the source example report?
A facility with lighting, power, HVAC and mechanical connected loads totaling 200 kW has a calculated maximum demand of 160 kW using a demand factor of 0.80.
Can this preliminary calculation be used as final design approval?
Preliminary load calculation only. Final electrical sizing shall be validated against the approved load schedule, project design criteria and applicable electrical standards.
What should be checked before final selection or implementation?
Verify all connected loads and the adopted demand factor against the approved load schedule. Consider diversity, motor starting loads, future expansion and standby systems.